Project Plan & Work Breakdown Structure (WBS)

Project Plan & Work Breakdown Structure (WBS)

Project: School Management System (SMS) Version: 1.0 Date: 12 August 2025 Prepared By: Abhi Soft


1. Document Control

Version Date Author Description
1.0 12 Aug 2025 Project Manager Initial Draft

2. Project Overview

The School Management System project will develop a centralized web and mobile ERP solution for schools to manage academic, administrative, and communication activities efficiently. The project will be completed in 5 main phases: Initiation, Planning, Execution, Testing, and Deployment.


3. Project Objectives

  • Deliver a secure, scalable ERP platform for school management.
  • Streamline processes for admissions, attendance, exams, fees, and communication.
  • Ensure seamless integration with GPS and payment gateways.
  • Provide role-based dashboards for different user types.

4. Project Timeline (High-Level)

Phase Start Date End Date Duration
Initiation 12 Aug 2025 19 Aug 2025 1 week
Planning 20 Aug 2025 04 Sep 2025 2 weeks
Execution (Development) 05 Sep 2025 30 Oct 2025 8 weeks
Testing & QA 01 Nov 2025 15 Nov 2025 2 weeks
UAT & Deployment 16 Nov 2025 05 Dec 2025 3 weeks

5. Work Breakdown Structure (WBS)

Level 1 – Main Project Phases Level 2 – Deliverables / Activities Level 3 – Subtasks


1. Initiation

1.1 Project Charter Creation 1.2 Feasibility Study 1.3 Stakeholder Identification & Approval


2. Planning

2.1 Requirements Gathering & Analysis   2.1.1 Conduct stakeholder interviews   2.1.2 Collect business and functional requirements 2.2 Business Requirements Document (BRD) Creation 2.3 Software Requirements Specification (SRS) Creation 2.4 Risk Management Plan 2.5 Communication Plan


3. Execution (Development)

3.1 System Design   3.1.1 Database Design   3.1.2 Architecture Diagram   3.1.3 UI/UX Wireframes 3.2 Backend Development   3.2.1 API Development   3.2.2 Module Development (Admissions, Attendance, etc.) 3.3 Frontend Development   3.3.1 Web Interface   3.3.2 Mobile App Interface 3.4 Integration   3.4.1 Payment Gateway Integration   3.4.2 GPS Bus Tracking Integration


4. Testing

4.1 Test Plan Creation 4.2 Unit Testing 4.3 Integration Testing 4.4 System Testing 4.5 User Acceptance Testing (UAT)


5. Deployment & Closure

5.1 Deployment to Production 5.2 User Training & Documentation 5.3 Project Closure Report 5.4 Post-Implementation Support


6. Roles & Responsibilities

Role Responsibility
Project Manager Overall coordination, risk management
Development Team System design, coding, integrations
QA Team Testing & defect management
School IT Team Local setup & maintenance
Trainers Conduct end-user training

7. Risk Management

Risk Impact Mitigation
Requirement delays Medium Early stakeholder involvement
Scope creep High Strict change request process
Integration issues Medium Early API testing