Sample Resource Plan Document for a School Management System

Resource Plan

Project: School Management System (SMS) Version: 1.0 Date: 12 August 2025 Prepared By: Abhi Soft


1. Document Control

Version Date Author Description
1.0 12 Aug 2025 Project Manager Initial Draft

2. Purpose

The purpose of this Resource Plan is to identify and allocate human, technical, and financial resources required for the successful completion of the School Management System project. This plan ensures optimal utilization of resources while maintaining project timelines and quality.


3. Resource Categories

The resources required for the project are divided into the following categories:

  • Human Resources – Project team members with defined roles and responsibilities.
  • Technical Resources – Hardware, software, and tools.
  • Financial Resources – Budget allocation for development, testing, and deployment.

4. Human Resource Allocation

Role Name/To Be Assigned Responsibility Allocation (%) Duration
Project Manager John Smith Project planning, execution, monitoring 50% Full project
Business Analyst Priya Sharma Requirements gathering & BRD creation 40% Initiation & Planning
UI/UX Designer Rahul Mehta Wireframes, prototypes, and UI design 100% Design phase
Backend Developer To Be Assigned API & database development 100% Execution
Frontend Developer To Be Assigned Web and mobile front-end development 100% Execution
QA Engineer Anjali Verma Test planning & execution 80% Testing phase
DevOps Engineer To Be Assigned Deployment & CI/CD 50% Deployment phase
Trainer To Be Assigned User training & documentation 50% Post-deployment

5. Technical Resources

Resource Description Purpose Quantity Duration
Development Laptops High-performance laptops Development 6 Full project
Server Hosting (Cloud) AWS EC2 / Azure Hosting application backend 1 Full project
Database Server MySQL/PostgreSQL Data storage 1 Full project
Design Tools Figma, Adobe XD UI/UX design Licenses for designers Planning & Design
Development Tools VS Code, GitHub Coding & version control Licenses for devs Execution
Testing Tools Selenium, Postman Test automation 2 licenses Testing phase
Communication Tools Slack, Zoom Team communication 1 license per member Full project

6. Financial Resources (Estimated Budget)

Resource Category Estimated Cost (INR) Notes
Human Resources ₹12,00,000 Salaries/Contract fees
Technical Resources ₹3,50,000 Hardware & software
Cloud Hosting ₹1,00,000 AWS/Azure for 1 year
Training & Documentation ₹50,000 End-user training
Contingency ₹1,00,000 Risk buffer
Total ₹18,00,000

7. Resource Utilization Timeline

Phase Key Resources Used
Initiation Project Manager, Business Analyst
Planning BA, UI/UX Designer
Execution Developers, Designer, DevOps
Testing QA Engineer, Developers
Deployment DevOps, Trainer
Post-Go-Live Support PM, QA, DevOps

8. Risk & Mitigation

Risk Impact Mitigation
Resource unavailability High Maintain backup team members
Budget overrun Medium Monitor expenses monthly
Tool/license expiration Low Auto-renewal setup